About intermediate inspection of building (June 1, 2020 ...)

The last update date:

 Based on regulations of 3 Paragraph 1 No. 2 of Building Standard Act Article 7 and No. 6, we appoint specific processes of building performing intermediate inspection and carry out intermediate inspection from June 1, 2000.

 We carry out intermediate inspection sequentially from June 1, 2020. 

 

About intermediate inspection that Saga determines (Saga-shi establishes the Saga city separately.)

 

 Building targeted for intermediate inspection must undergo intermediate inspection if we finish construction pertaining to process (specific process) appointed depending on structure of building. In addition, we cannot continue the later construction (process after specific process) if we do not pass intermediate inspection. 

 

  • Area that performs intermediate inspection        The whole area of Saga except Saga-shi
  • Building (※ 1) which is targeted for intermediate inspection

 Use : Special building (law separate table first (thing which is, and advocates in (4) from) column (1))

 Scale : The third floor (we remove basement.) The-based above or total floor area exceeds 1,000 square meters

 

[process after specific process and specific process]

Building

It is structure of this

Time to perform intermediate inspection

(specific process) (※ 2)

Construction to be possible after the inspection pass

(process after specific process)

Wooden construction

・How to build pillar, needle and strut construction

・Two-by-four method constructs setting of bearing wall

・The exterior work of wall or interior construction

Steel-frame building

・How to build the first-floor steel frames construction

・Construction to arrange fireproof coating to cover steel frame of main part in structure proof stress or the exterior work of wall or interior construction

Steel reinforced concrete construction

・Construction to locate reinforcing rod to needle in support of floor (roof is edition when number of floors is 1) on the second floor and this

・Installation construction that floor on the second floor is for as for the thing which does not perform the construction concerned on the site (roof is edition when number of floors is 1)

・Concrete ground fishing construction to cover reinforcing rod located to needle in support of floor (roof is edition when number of floors is 1) on the second floor and this

・Thing which does not perform the construction concerned on the site constructs installation of the second-floor pillar or wall (construction to cover part which joins the first-floor wall to roof version when number of floors is 1)

Steel frame reinforcing rod

Concrete

・How to build the first-floor steel frames construction

・Concrete ground fishing construction to cover steel frame of main part in structure proof stress

Other than above

It is structure of this

・Construction to place reinforcing rod in the basics

・Basic concrete ground fishing construction

※Building which is building receiving application of building (buildings obliged to carry out intermediate inspection uniformly of the whole country) including process of 3 Paragraph 1 first of 1 method Article 7, law Article 18 (buildings such as country, the prefecture) or law Article 85 (temporary building), 20 certification model materials of law Article 68 does not apply.

※Building which used structure 2 2 or more together comes close to the majority structure division of floor space on the first floor.

 

About national intermediate inspection setting uniformly

 By law revision of June 20, 2007, as for the following building, intermediate inspection is required in national uniformity. (3 Paragraph 1 first relations of law Article 7) 

  • Target building : Apartment house which has 3 or more number of floors
  • Specific process : Process of construction to locate reinforcing rod to needle in support of floor on the second floor and this

Application fee

 
  • Intermediate inspection application fees are as follows.

The total of floor space of part performing intermediate inspection

Sum of fee

Thing within 30 square meters

13,000 yen

More than 30 square meters, thing within 100 square meters

16,000 yen

More than 100 square meters, thing within 200 square meters

22,000 yen

More than 200 square meters, thing within 500 square meters

28,000 yen

More than 500 square meters, thing within 1,000 square meters

49,000 yen

More than 1,000 square meters, thing within 2,000 square meters

66,000 yen

More than 2,000 square meters, thing within 10,000 square meters

147,000 yen

More than 10,000 square meters, thing within 50,000 square meters

222,000 yen

We exceed 50,000 square meters

407,000 yen

  • Calculation of floor space of part performing intermediate inspection is as follows.

 ・ In the case of wooden construction: Total floor area

 ・ In the case of steel-frame building, steel reinforced concrete construction or steel frame steel reinforced concrete construction: The total of the following floor space on the second floor

 ・ In the case of structure (process specific basic construction to arrange) except the above: Floor space of lowest floor

 

※ As mechanic ward of all becomes a target of intermediate inspection in the case of construction to mediate in plural mechanics ward, and to perform, please calculate floor space of part performing intermediate inspection for each mechanic ward of each.

 Way of thinking of target building

 

 When the third-floor (we remove basement.)-based above or total floor area exceeds 1,000 square meters, it is for part (when there is multiple the whole application part) affecting new construction, enlargement concerned or reconstruction as "one building". Please confirm at Building Control Section (management section) window of each engineering works office.

※ Please refer to Saga-shi government office Building Guidance Division (TEL 0952-40-7170) for the Saga city.

※ Intermediate inspection takes even private confirmation inspection engine. 

Attached file


 


 


 

We relate to this page
Inquiry
(ID: 14656)
Saga prefectural government office (corporation number 1000020410004) 〒 840-8570  1-1-59, Jonai, Saga-shi   Tel: 0952-24-2111 (main)     
Copyright© 2016 Saga Prefecture.All Rights Reserved.

Saga prefectural government office (corporation number 1000020410004)

〒840-8570
1-1-59, Jonai, Saga-shi
Tel: 0952-24-2111 (main)
Copyright© 2016 Saga Prefecture.All Rights Reserved.