To the Saga synthesis top

We revise guide of Saga construction global assessment successful bid method paperwork (April 1, 2019 revision)

The last update date:

We revise guide of Saga construction global assessment successful bid method paperwork by the following.

 

[this revision point]

 

  ・About self-marking type (pavement), we revised construction targeted for the average of construction results of company by the following about construction results in ability for construction of company.

     (the revised front) The average of all construction results rating points amount of last contract 10 million yen or more

         ⇊        ⇊

     (after the revision) The average of all construction results

 

  ・The number of the letters of technical views

 

  ・Correction, addition of words such as other revised leaks

 

 

 

 

 

The changes of revision such as the points of past Saga construction global assessment method

 

[revision (July, 2018) of guide]

  • In the paving work (Class A: 18 1 million yen - 25 1 million yen), we added global assessment successful bid method "self-marking type pavement B".
  • In the landscape gardening construction (15 1 million yen - 60 1 million yen), we added global assessment successful bid method "self-marking type landscape gardening". 

 

[revision (April, 2018) of guide]

  • We performed review of evaluation standard about technical suggestion, way of thinking of evaluation of simple construction plan.
  • In addition, we performed some corrections of words.

 

[revision (December 1, 2017) of guide]

  • We perform some addition of words.                                                                           We added o where "it was not said that commendation as specific construction joint venture was targeted for evaluation." in instructions of excellent construction construction that was end-point of successful bidder decision standard.                                                             

 

[revision (July 17, 2017) of guide]

  • We perform some corrections of words.                                                                           Facilities construction pertaining to building complete set construction before revision                                                             We construct facilities pertaining to building after the revision

 

 [revision (July 1, 2017) of guide]

  • In the engineering works complete set construction (Class B: 20 million yen - 30 million yen), we try global assessment successful bid method "self-marking type D".
  • In addition, we perform some corrections of words.

 

 [revision (April, 2017) of guide]

  • About a part of one set of engineering work (* Class A) self-marking type B, we add global assessment successful bid method "technique suggestion challenge model".
  • We did target period of "experience in response to commendation" in excellent construction construction with the past two years.
  • We did period targeted for construction results with the past three years and abolished results that we added quarterly.
  • We added setting for term of works when there was cancellation period about "term of works" of construction experience of similar construction and construction in neighbor.
  • In addition, we perform some corrections of words. 

 

[revision (September, 2016) of guide]

  • We add evaluation by "holdings construction" in self-marking type C.
  • In addition, we perform some corrections of words.

 

[revision (September, 2015) of guide]

  • About construction that became targeted for selection of excellent construction commendation, it is said that it is targeted for evaluation of excellent construction construction of global assessment successful bid method.
  • We change evaluation point assignment of item of construction experience of construction in neighbor of simple model B of engineering works complete set construction and simple model C.

  

[revision (July, 2015) of guide] 

  • In building complete set construction (150 million yen - 500 million yen), facilities construction (electricity and tubing) (60 million yen - 100 million yen) pertaining to building complete set construction, we try self-marking type. 

  

[revision (April, 2015) of the point and guide] 

  We revise the Saga construction construction system's confirmation type global assessment successful bid method conduct point and guide with revision of ordering standard on April 1, 2015.

 

(revision point of the point) 

  • We changed construction targeted for confirmation of the construction system pertaining to engineering works complete set construction type to construction with 70 million yen or more design price.
  • We revised "guide of Saga construction global assessment successful bid method paperwork". 
  • As for the conduct point after revision, the guide of paperwork, please see attached file. 

 

 (revision point of guide)

  • About one set of engineering work, we did amount of money targeted for global assessment successful bid method 30 million yen or more.
  • It continues in 2015 and, about self-marking type B, C, tries.
  • We add self-marking type to global assessment successful bid method and, about pavement, slope, specialized construction of landslide, try.
  • In addition, we perform some corrections of words.

 

Attached file

The Saga global assessment successful bid method conduct point With new window

(426KB, zip compressed file)

The Saga global assessment successful bid method construction system's confirmation type material making point With new window

(324KB, zip compressed file)

The Saga global assessment successful bid method construction system's confirmation type (collection of styles) With new window

    We relate to this page
    Inquiry
    (ID: 25913)
    Saga prefectural government office (corporation number 1000020410004) 〒 840-8570  1-1-59, Jonai, Saga-shi   Tel: 0952-24-2111 (main)     
    Copyright© 2016 Saga Prefecture.All Rights Reserved.

    Saga prefectural government office (corporation number 1000020410004)

    〒840-8570
    1-1-59, Jonai, Saga-shi
    Tel: 0952-24-2111 (main)
    Copyright© 2016 Saga Prefecture.All Rights Reserved.