To the Saga synthesis top

It is Notifecations about septic tank and style (toward the septic tank establisher)

The last update date:
 

Notifecations about septic tank

 
 It is procedure that is necessary before we abolish from setting for septic tank.
 Procedure when we change septic tank which we installed when septic tank is installed and abolish,
 Please refer to each the prefecture Public Health and Welfare Office having jurisdiction over setting place of septic tank.
 (in the case of Saga city limits, please refer to Saga-shi Waterworks and Sewerage Bureau.)
 
 

List of Notifecations point, reference prefecture Public Health and Welfare Office or Saga-shi office

Office name

Address

Phone number, FAX number

Jurisdiction

Central Saga Public Health and Welfare Office

(except Saga-shi)

Saga-shi ⼋ chonawatecho 1-20

Telephone: 0952-30-1907

FAX: 0952-33-4632

Taku-shi

⼩ castle town

Kanzaki-shi

Yoshino, Kanzaki-gun ka ⾥ town

Tosu Public Health and Welfare Office

⿃ home city 1234-1, Motomachi

Telephone: 0942-83-6820

FAX: 0942-84-1849

⿃ home city

Miyaki-gun basis ⼭ town

Kamimine-cho, Miyaki-gun

Miyaki-cho, Miyaki-gun

Karatsu Public Health and Welfare Office

Karatsu-shi ⼤ name ⼩ road 3-1

Telephone: 0955-73-1179

FAX: 0955-75-1176

Karatsu-shi

The Higashimatsuura-gun ⽞ sea-cho

Imari Public Health and Welfare Office

Italy ten thousand ⾥ city Shintencho Hill ⼝122-4

Telephone: 0955-23-2103

FAX: 0955-22-3853

Italy ten thousand ⾥ city

⻄ matsuuragunyu ⽥ town

Kito Public Health and Welfare Office

265, Takeochoshowa, Takeo-shi

Telephone: 0954-23-3506

FAX: 0954-22-4573

Takeo-shi

⿅ island city

Ureshino-shi

Kishima-gun ⼤ town town

Kouhoku-machi, Kishima-gun

Kishima-gun ⽩⽯ town

Tara-cho, Fujitsu-gun

 
 ※In the case of Saga city limits, please refer to Saga-shi Waterworks and Sewerage Bureau. Telephone: 0952-34-5047
 
  

Explanation (we can download style most from bottom) of various Notifecations

 
* Septic tank setting notification form
 We take consideration into and abolish expression rest room or independent septic tank and install merger septic tank, and Notifecations is necessary when we install septic tank. 
 Notifecations needs Part 2.
 <attachment>
  (1) Plan in site of building and each floor ground plan (fill in each dimension. In addition, when there are well and expression water tank under the ground,
     When you fill in the position and distance to septic tank and do area calculation by) people tank calculation, attach figure of mensuration calculation.

  (2) Drainage plumbing figure out of the indoor

  (3) Figure of septic tank structure

  (4) Design check (when the staff targeted for disposal of septic tanks in model authorization is indefinite when it is to model authorization septic tank.)

  (5) -Documents (we say "the standard method" Building Standard Act (as follows.10 Paragraph 1 of) Article 68 which prove model authorization when it is to 1 model authorization septic tank

     Model authorization book based on model conformity authorization book based on this and law Article 13 (or Article 16))

  (5) -When is to septic tank which does not catch 2 model authorization, processing flow sheet and specifications (capacity calculation, figure of sequence to arrange, and to calculate, and to arrange

     We include septic tank (the existing getting nervous) structure relations check list (the paperwork point style first).)

  (5) -It is Building Standard Act enforcement order with septic tank of structure method except structure method (1980 Ministry of Construction notification No. 1292) that 3 Ministers of Land, Infrastructure and Transport set

     When is to septic tank needing authorization of meeting regulations of Article 35 Paragraph 1, authorization book based on 26 Paragraph 1 of standard method Article 68

  (6) Identification of examination for septic tank setting situation request reception desk finished based on law Article 7

  (7) Written oath (paperwork point style No. 2) about setting of septic tank or management

  (8) We are equivalent to copy of trust contract with septic tank maintenance check supplier or that

  (9) Have been attended septic tank establisher class; copy of paper (when cannot take lectures out of necessity by report of setting kiyomekasoshiyokaishihotsugeshohisage

     It is said that written oath) attendance eligible people of attending septic tank establisher class before appearance are as follows.

   <attendance eligible people of septic tank establisher class>

    Person planning setting of septic tank or person who becomes septic tank manager newly

House for individual

The septic tank establisher (manager) person or adult who lives together

Apartment complex

Person who has entitlement to about landlord of apartment complex, management of septic tank

(when it is in corporation, we include employee.)

Office

Employee in charge of septic tank management in office using septic tank

 

  (10) When the staff targeted for processing must employ technical manager in 501 or more, dossier ((a) and (b) or (c)) listed below

   (a) Copy of septic tank management person certificate

   (b) The staff targeted for processing engaged in business about maintenance check of septic tank of more than 501 scales and technical duties about cleaning more than two years

     (thing which matched work experience of cleaning with maintenance check of septic tank) documents which prove the effect

   (c) Copy of identification of septic tank technology manager class completion
      But attach at the time of beginning to use report of septic tank when technical manager is not selected.

    ※(b) It is desirable to attend case, septic tank technology manager class of this.

  (11) Documents which admit that other Public Health and Welfare Office head is necessary

 

* Septic tank change notification form

 When we change structure of septic tank or scale, Notifecations is necessary.

 Notifecations needs Part 2.

 <attachment>

  Documents which are related to change among the above, attached documents of septic tank setting notification form.

 

* Report (change of matter) about septic tank

 The items mentioned (establisher address, the place name lot number of setting place, discharge, construction supplier, maintenance check trust supplier, building of report of septic tank setting or notification of change

 When change produces use, total floor area, the plumbing in), submission is necessary for (change pertaining to law Article 5, 2 Paragraph 2 of Article 10 and Paragraph 3 is excluded.).

  <attached documents>

 (1) When we change maintenance check supplier
   ・Copy of trust contract with septic tank maintenance check supplier

 (2) When we change total floor area, the plumbing
   ・Drawing pertaining to change

  

* Septic tank beginning to use report

 Septic tank manager needs Notifecations within 30 days from day of septic tank beginning to use if we start use of septic tank.

 <attached documents>

  (1) Maintenance check record just before beginning to use

  (2) Construction photograph

    Every next process, we photographed with construction name, blackboard which we filled in names of septic tank on on the shooting date and surveying pole.

  But it is authorized septic tank of municipalities setting type and can omit when municipalities perform construction management.

   (a) Photograph indicating what septic tank facilities person supervises for conduct

   (b) The septic tank body (thing understanding model including plate)

   (c) Photograph indicating the situation of foundation work (we arrange the chestnut-large shingle ground business and concrete)

   (d) Photograph (thing showing the situation that performs dampening a sheet of paper, tightens backfill water while keeping stability and hits, and performs hardening) at the time of the body installation

   (e) Photograph indicating the situation of the upper part slab construction (arrange and concrete)

   (f) When reinforcement such as withstand pressure versions and padding are necessary; photograph indicating the situation

   (g) Photograph of the setting situation (thing knowing the basics and the height of the ground) of blower

  (3) When do not attach documents about technical manager in setting Notifecations of septic tank requiring technical manager, dossier listed below

           ((a) and (b) or (c))    

   (a) Copy of septic tank management person certificate

   (b) The staff targeted for processing engages in business about maintenance check of septic tank of more than 501 scales and technical duties about cleaning more than two years

                Documents which prove the ta (thing which matched work experience of cleaning with maintenance check of septic tank) effect

   (c) Copy of identification of septic tank technology manager class completion

  (4) When do not attach copy of trust contract with septic tank maintenance check supplier in setting Notifecations, copying of trust contract

 

* Technical manager change report

   We attach the next material ((1) and (2) or (3)), and septic tank manager needs submission immediately if we change technical manager.

 <attached documents>

  (1) Copy of septic tank management person certificate

  (2) The staff targeted for processing engages in business about maintenance check of septic tank of more than 501 scales and technical duties about cleaning more than two years

     Documents which prove the ta (thing which matched work experience of cleaning with maintenance check of septic tank) effect   

  (3) Copy of identification of septic tank technology manager class completion

 

* Septic tank manager change report

 Septic tank manager needs submission immediately if we produce change.

  <attached documents>

  (1) Copy of trust contract with septic tank maintenance check supplier.

  (2) Written oath of having been attended septic tank establisher class, and attending copy of paper or establisher class

  (3) But it is managed written oath (paperwork point style No. 2) about setting of septic tank or management by interfamily change appropriately

     When we can confirm in the examination for rukotoga provision, we can omit (1) (2).

 

* Use of septic tank stop notification form

 Septic tank manager can submit if we clean the septic tank concerned in stop of use of septic tank.

 <attached documents>

  ・Record (copy of cleaning report) of cleaning

 

* Use of septic tank reopening notification form

 When restarted use of septic tank which notified of use stop or if use of the septic tank concerned knows what is reopened, the purification concerned

 It is 30 from day when we restarted use of cistern or day when we restarted use of the septic tank concerned or day when use of the septic tank concerned knew what is reopened

 Submission is necessary within day.

 <attached documents>

  ・Copy of trust contract with septic tank maintenance check supplier

 

* Report (withdrawal) about septic tank

 Person who is going to install septic tank newly is * with septic tank with septic tank setting notification form or public septic tank setting plan discussion offer book after the submission concerned

 When you cancel before you do oki, submit.

 

* Use of septic tank abolition notification form

 Septic tank manager needs submission within 30 days from day of the abolition if we abolish septic tank.

 <attached documents>

  ・Copy of septic tank cleaning report

  

Word Use of septic tank abolition notification form We open with the other window(word: 22.1 kilobytes)

We relate to this page
Inquiry
(ID: 73997)
Saga prefectural government office (corporation number 1000020410004) 〒 840-8570  1-1-59, Jonai, Saga-shi   Tel: 0952-24-2111 (main)     
Copyright© 2016 Saga Prefecture.All Rights Reserved.

Saga prefectural government office (corporation number 1000020410004)

〒840-8570
1-1-59, Jonai, Saga-shi
Tel: 0952-24-2111 (main)
Copyright© 2016 Saga Prefecture.All Rights Reserved.