About taking two days off at the weekend trial construction in harbor construction

The last update date:

Toward realization of work-style reform of construction industry, we carry out "taking two days off at the weekend trial construction" in harbor construction of Saga from July 30, 2020.

 

 ●During the target period, we find vacation that is beyond rest for 8 for four weeks "to take two days off at the weekend", and perfection blind alley does the construction spot.

 ●"Target period" is periods (in summer holidays, factory production periods are excluded for New Year holidays.) from construction start day to construction completion day.

 

■Construction that is targeted for trial

 

 Harbor construction that Department of Land Development and Department of Regional Exchange order ※We did this and stated that it was taking two days off at the weekend trial construction clearly in special mention specifications.

 ※We multiplied using "harbor contract construction multiplication standard" with the harbor construction here and placed an order.

 

 But, about the following construction, construction targeted for trial is not intended.

 ・When there is limitation in the completion time and working hour

 ・When disaster recovery efforts are urgent

 ・Construction except harbor construction

 

■Conduct method

 

 Person of order shall submit yes or no that you wish to carry out by one of construction plan submission on 2nd on weekly holiday to overseer with construction meeting book.

 

■Application

 

 We apply from construction to notify publicly after July 30, 2020.

 

■Others

 

 ・In order person who hoped for 2nd on weekly holiday being "taking two days off at the weekend trial construction", clear statement is necessary by construction signboards.

 ・When we can achieve the spot blind alley where is beyond rest for 8 for four weeks, we have revision (increase) of labor cost by correction factor.

 ・When we can achieve the spot blind alley where is beyond rest for 6 for four weeks, we add in the construction results rating and evaluate. (there is no deduction when we were not able to be accomplished.)

 

※For more details, please confirm the following point.


 

 

 

We relate to this page
Inquiry
(ID: 75663)
Saga prefectural government office (corporation number 1000020410004) 〒 840-8570  1-1-59, Jonai, Saga-shi   Tel: 0952-24-2111 (main)     
Copyright© 2016 Saga Prefecture.All Rights Reserved.

Saga prefectural government office (corporation number 1000020410004)

〒840-8570
1-1-59, Jonai, Saga-shi
Tel: 0952-24-2111 (main)
Copyright© 2016 Saga Prefecture.All Rights Reserved.